New Transmission Lines In Texas Will Transport Renewables

Author:Solar Industry     Source:Solar Industry     Click:341     Publish time:2013/4/3 11:50:24

Lone Star Transmission LLC, a subsidiary of NextEra Energy Inc., has energized approximately 330 miles of new 345 kV transmission lines and associated transmission facilities. The project runs from Scurry County, northwest of Abilene, Texas, to Navarro County, south of Dallas. Four circuits and five substations are a part of the new infrastructure.

Lone Star's transmission lines are contributing to the state's transmission grid improvement program, which will see the addition of approximately 2,300 miles of 345 kV lines designed to deliver power from the Competitive Renewable Energy Zones (CREZ) in West Texas and the Texas Panhandle to the Dallas/Fort Worth area and other population centers. Lone Star says it is the first new transmission utility to energize its CREZ facilities.

The company says it used more than 2,500 spun concrete monopoles to complete the project, which helped reduce the project's visual impact and land needs without adding costs.


Keywords:New Transmission Lines In Texas Will Transport Renewables
更多
Related information

0 Comments

Comments List
Comment
Name:
 
Level:
1 2 3 4 5  
Content:
 
Verification code:
RefreshCan't See clearly?

Today

Picture news

Beijing 12023756
 

ESCN

News department:Tel: +86-10-65001167 E-mail:edit@escn.com.cn

Address:Room 1007A, Huashang Building, No.2 Yanjingxili, Chaoyang District,Beijing

Copy Right 2011-2012 All Rights Reserved Powered By I5tool.com Illegal Information Reporting